Fixed Asset Expenditure Form
EL-FIN-F004 Rev 1
FIXED ASSET EXPENDITURE FORM
Date: 2014-04-14
Asset Name: Progress payment for Building Construction
Asset Serial Number: nill
Asset Category: Building Improvements-EL
Asset Description: Progress payment for Building Construction
Purpose Required For: nill
Location: BARROW IKOYI
Qty: 1
Unit Cost: 4,489,776
Total Cost: 4,489,776
Supplier:
Purchase Price: 4,489,776
Purchase Date: 2014-04-14
Insured Value: nill
Capex Budgets: 0
Capex Order: 0
Scrap Value: 4,489,776
Depreciation Start Date: 2014-04-14
Depreciation Method: Straight-line
Accounting Period in month(s): 1
Cost Centres: 0
- 11 April. 2022
-
11:06:35 AM
Daniel Abah ( Internal Audit )
Fixed Asset: "900739" was sent back requestor - 11 April. 2022
-
11:06:13 AM
Daniel Abah ( Internal Audit )
Fixed Asset: "900739" was sent back requestor - 11 April. 2022
-
11:03:58 AM
Daniel Abah ( Internal Audit )
Fixed Asset: "900739" was updated by Audit - 11 April. 2022
-
11:03:36 AM
Daniel Abah ( Internal Audit )
Fixed Asset: "900739" was updated by Audit - 11 April. 2022
-
10:35:10 AM
Philip Odekina ( Finance Manager )
Fixed Asset: "900739" was updated by HOD - 01 April. 2022
-
02:24:14 PM
Ume Obuba ( Finance/Procurement )
Fixed Asset: "900739" was created